A1 Rainton Crossroads

You are here: Home » Futures » A1 Rainton Crossroads

CBRD Futures is no longer being updated as of July 2012 and information on this page may now be out of date.

Type
Road for use by all traffic
Status
Completed
Authority
Highways Agency
Cost
Unknown
Finance
Central Government
Timescale
2003-2004
Length
Unknown

Scheme Outline

A small scale junction improvement scheme at the dangerous Rainton crossroads. Currently this is a flat junction just a few miles north of the end of the motorway at Dishforth. The A1 here is due to be upgraded to motorway within the next few years anyway, but this junction is seen as such a priority that it is to be grade separated immediately. A flyover will be constructed but the exact layout of the new junction is not yet confirmed.

Progress

14 April 2004 Bridge embankments, complete with retaining walls, under construction.
14 August 2004 The bridge span is now in place and works on the junction are progressing.
14 October 2004 Works are completed.

It's over!