A10 Wadesmill - Colliers End
You are here: Home » Futures » A10 Wadesmill - Colliers End
CBRD Futures is no longer being updated as of July 2012 and information on this page may now be out of date.
- Type
- Road for use by all traffic
- Status
- Completed
- Authority
- Highways Agency
- Cost
- Unknown
- Finance
- Central Government/DBFO
- Timescale
- 2002-2004
- Length
- 6.4 km (4 miles)
Scheme Outline
Construction of a bypass for the villages of Wadesmill, High Cross and Colliers End. The bypass will be to dual-two lane standard with grade-separated junctions, extending the A10 dualled route from its current terminus north of Ware to the A120 roundabout at Puckeridge.
Progress
| 14 December 2003 | The expected opening date for the scheme is missed as severe ground settlement causes the road surface to break up. The Highways Agency is unable to give a date when the road will open. |
|---|---|
| 14 October 2004 | Extensive works to rebuild sections of the bypass following subsidence problems have been completed and the road is open to traffic, ten months after the programmed opening date. |
It's over!
This scheme has been completed, so it's no longer possible to edit any of the information on this page.
This scheme was last updated on 26 October 2008.