A1033 Hedon Road Upgrade

You are here: Home » Futures » A1033 Hedon Road Upgrade

CBRD Futures is no longer being updated as of July 2012 and information on this page may now be out of date.

Type
Road for use by all traffic
Status
Completed
Authority
Highways Agency
Cost
Unknown
Finance
Highways Agency
Timescale
2000-2003
Length
6.4 km (4 miles)

Scheme Outline

Upgrade of the A1033 between Hull City Centre and the docks to dual two lane carriageways with some grade separated junctions. It will eliminate the present congested road with frequent traffic lights and access points.

It's over!

This scheme has been completed, so it's no longer possible to edit any of the information on this page.

This scheme was last updated on 13 October 2008.