- Type
- Road for use by all traffic
- Status
- Completed
- Authority
- Highways Agency
- Cost
- Unknown
- Finance
- Highways Agency
- Timescale
- 2000-2003
- Length
- 6.4 km (4 miles)
Scheme Outline
Upgrade of the A1033 between Hull City Centre and the docks to dual two lane carriageways with some grade separated junctions. It will eliminate the present congested road with frequent traffic lights and access points.