A11 Attleborough Bypass Improvement
You are here: Home » Futures » A11 Attleborough Bypass Improvement
CBRD Futures is no longer being updated as of July 2012 and information on this page may now be out of date.
- Type
- Road for use by all traffic
- Status
- Completed
- Authority
- Highways Agency
- Cost
- £ 25m
- Finance
- Central Government
- Timescale
- 2006-2007
- Length
- 5.5 km (3 miles)
Scheme Outline
An upgrade of the existing single-carriageway Attleborough Bypass to dual-two lane road, including an upgrade of the junctions along the route. This will grade separate the route, except at the southern end of the scheme, where the existing roundabout will be left in place.
Progress
| 14 December 2005 | Advance works have now started. |
|---|---|
| 14 June 2006 | Ground clearance has now taken place to the north of the existing road and bridgeworks have begun at the Watton Road junction. The whole bypass is now restricted to 40mph with no overtaking permitted. |
| 14 August 2006 | A 400m section of dual carriageway has been completed (including road markings) parallel to the southern end of the bypass. Other works are also progressing well.</p>October 2006 |
| 14 March 2007 | The scheme is completed. |
It's over!
This scheme has been completed, so it's no longer possible to edit any of the information on this page.
This scheme was last updated on 26 October 2008.