A38 Taunton Third Way
You are here: Home » Futures » A38 Taunton Third Way
CBRD Futures is no longer being updated as of July 2012 and information on this page may now be out of date.
- Type
- New road for use by all traffic
- Status
- Completed
- Authority
- Somerset CC
- Cost
- £ 5.5m
- Finance
- Somerset CC/Central Government
- Timescale
- 2010-2011
- Length
- 0.5 km (0.3 miles)
Scheme Outline
Town centre link road, including a new bridge over the River Tone. Most of the route involves the realignment of existing streets and junction improvements.
Progress
| 28 September 2011 | This was officially opened yesterday, although doesn't seem to be signposted as open at either end! |
|---|
More information
- Official website
- somerset.gov.uk/.../Initiatives/Taunton Third Way
It's over!
This scheme has been completed, so it's no longer possible to edit any of the information on this page.
With thanks to Austin for information on this page.
This scheme was last updated on 30 September 2011.