A43 Upgrade
You are here: Home » Futures » A43 Upgrade
CBRD Futures is no longer being updated as of July 2012 and information on this page may now be out of date.
- Type
- Road for use by all traffic
- Status
- Completed
- Authority
- Highways Agency
- Cost
- £ 56.6m
- Finance
- Central Government
- Timescale
- 2000-2002
- Length
- 16 km (10 miles)
Scheme Outline
Upgrade of A43 between Towcester and the M40 to dual two lane standard, including some realignment. Also includes reconstruction of the junction with the M40.
Progress
| 14 November 2010 | Construction work begins. |
|---|---|
| 14 November 2010 | Completion date of Summer 2002 is missed. Work is, however, almost complete by Autumn. |
It's over!
This scheme has been completed, so it's no longer possible to edit any of the information on this page.
This scheme was last updated on 22 October 2008.