A43 Upgrade

You are here: Home » Futures » A43 Upgrade

CBRD Futures is no longer being updated as of July 2012 and information on this page may now be out of date.

Type
Road for use by all traffic
Status
Completed
Authority
Highways Agency
Cost
£ 56.6m
Finance
Central Government
Timescale
2000-2002
Length
16 km (10 miles)

Scheme Outline

Upgrade of A43 between Towcester and the M40 to dual two lane standard, including some realignment. Also includes reconstruction of the junction with the M40.

Progress

14 November 2010 Construction work begins.
14 November 2010 Completion date of Summer 2002 is missed. Work is, however, almost complete by Autumn.

It's over!

This scheme has been completed, so it's no longer possible to edit any of the information on this page.

This scheme was last updated on 22 October 2008.