A556 Knutsford to Bowdon Environmental Improvement

You are here: Home » Futures » A556 Knutsford to Bowdon Environmental Improvement

Type
Bypass or realignment for use by all traffic
Status
In planning or on hold
Authority
Highways Agency
Cost
£ 142m
Finance
Central Government
Timescale
2013-2015
Length
8.0 km (5.0 miles)

Scheme Outline

A new largely offline and grade separated dual carriageway linking M6 J19 and M56 J7. It would replace the current heavily congested and mostly four lane single carriageway A556.

Progress

18 January 2009 The preferred route was announced by the Highways Agency in December 2008.
23 March 2010 Details of the amended preferred route were released on 19 March 2010. Construction is now expected to start in 2013.
27 October 2010 Funding for this scheme was confirmed in a statement by the Transport Secretary yesterday.
17 January 2011 It was announced today that Costain has been appointed as contractor for this scheme. Construction is scheduled to start before 2015.
23 January 2012 A public consultation on the scheme starts today and runs until 16 April 2012.

More information

Official website
highways.gov.uk/roads/projects/14909.aspx

With thanks to Michael Pritchard for information on this page.

This scheme was last updated on 23 January 2012.