A69 Haydon Bridge Bypass
You are here: Home » Futures » A69 Haydon Bridge Bypass
CBRD Futures is no longer being updated as of July 2012 and information on this page may now be out of date.
- Type
- Road for use by all traffic
- Status
- Completed
- Authority
- Highways Agency
- Cost
- £ 25m
- Finance
- Central Government
- Timescale
- 2007-2009
- Length
- 3.2 km (2.0 miles)
Scheme Outline
Construction of a new single-carriageway bypass to Haydon Bridge on the A69 Newcastle-Carlisle route. This is the last significant settlement on the route to receive a bypass.
The Highways Agency have declared their planned timescale for this project includes ground investigations beginning immediately, with construction beginning in 2007.
Progress
| 14 October 2006 | The government approves the scheme, with work due to start in 2007. |
|---|---|
| 14 January 2007 | Work begins on-site. |
| 14 June 2007 | Groundwork is now underway, with the line of the road clearly visible. Cemetery Road is now closed off for realignment works and construction of the bridge. |
| 24 March 2009 | The road is finished and open to traffic. |
More information
- Official website
- highways.gov.uk/roads/projects/5222.aspx
It's over!
This scheme has been completed, so it's no longer possible to edit any of the information on this page.
This scheme was last updated on 24 March 2009.