A1073 Spalding to Eye Improvement

You are here: Home - Futures - A1073 Spalding to Eye Improvement

Scheme Outline

Construction of a new single two-lane carriageway to replace the existing A1073 which connects Peterborough to Spalding via Crowland. The existing road is non-primary, but is preferred by traffic over the official A15/A16 routing via Market Deeping as it is more direct. As a result the A1073 is heavily overloaded, has a very poor accident record and is difficult to maintain.

It is expected that the resulting high-standard road will become a primary route on opening.

Project Statistics

Cost
£80.3m
Finance
Lincolnshire CC, Peterborough CC and Central Government grant
Estimated duration of works
2008-2010
Length of new road
22km (13.5 miles)

Progress

August 2007
Funding is confirmed by the Department for Transport. Having cleared all necessary public inquiries, the scheme is cleared to start in summer 2008.
February 2008
On 26th February, Rosie Winterton, a roads minister, dug the first sod on the project. Construction is now under way.

More information

Website
www.lincolnshire.gov.uk/section.asp?catid=15020

If you know more

If you have more details on this scheme - a correction to the information shown here or an update on the progress of works - please click here and share your knowledge.

With thanks to James Hewson, Jim Rayner and Gerry McKenna for information on this page.