Scheme Outline

Upgrade of the A14 route roughly between Cambridge and Huntingdon, in particular the stretch connecting the A1 and M11. The final route has yet to be selected but the improvement may include construction of a new dual-three lane route to bypass part of the existing road, with the remainder upgraded and widened substantially. The scheme also includes new interchange with the A1 and M11.

Project Statistics

Cost
Unknown
Finance
Highways Agency/TPI
Estimated duration of works
Unknown
Length of new road
18 miles

Progress

January 2007
With work on the realignment of the A14 not due to be complete until 2015, a shorter term proposal is made to upgrade the existing A1/A14 junction with a wider roundabout and traffic signals.
March 2007
Signalisation work has been completed.
October 2007
The full route for the A14 realignment has now been announced, with the final section to be made public comprising the new three-lane bypass to the south of Godmanchester. Construction is now expected to start in 2010.

More Information

Website
www.highways.gov.uk/roads/projects/4211.aspx

If you know more

If you have more details on this scheme - a correction to the information shown here or an update on the progress of works - please click here and share your knowledge.

Thanks to Jeff Bronks, Chris Cowdery, Tom Yarwood, Gerry McKenna, Keith Mason and Tom Banning for some information on this page.