A10 Wadesmill - Colliers End

You are here: Home - Futures - A10 Wadesmill - Colliers End

Scheme Outline

Construction of a bypass for the villages of Wadesmill, High Cross and Colliers End. The bypass will be to dual-two lane standard with grade-separated junctions, extending the A10 dualled route from its current terminus north of Ware to the A120 roundabout at Puckeridge.

Project Statistics

Cost
Unknown
Finance
Central government/DBFO
Estimated duration of works
Until 2004
Length of new road
4 miles

Progress

December 2003
The expected opening date for the scheme is missed as severe ground settlement causes the road surface to break up. The Highways Agency is unable to give a date when the road will open.
October 2004
Extensive works to rebuild sections of the bypass following subsidence problems have been completed and the road is open to traffic, ten months after the programmed opening date.

More Information

Website
www.highways.gov.uk