A1033 Hedon Road Upgrade
You are here: Home - Futures - A1033 Hedon Road Upgrade
Scheme Outline
Upgrade of the A1033 between Hull City Centre and the docks to dual two lane carriageways with some grade separated junctions. It will eliminate the present congested road with frequent traffic lights and access points.
Timeline
- 1833
- A Turnpike Act is passed for the construction of Hedon Road.
- 1987
- A Government White Paper strongly recommends the upgrade of the A1033.
- 2001
- The contract is finally awarded under the TPI (Targeted Programme of Improvements) scheme and work begins.
Project Statistics
- Cost
- Unknown
- Finance
- Central Government
- Estimated duration of works
- 2000-2003
- Length of works
- 4 miles
More Information
- Website
- www.hullaccess.co.uk