A13 Thames Gateway

You are here: Home - Futures - A13 Thames Gateway

Scheme Outline

Upgrade of the A13 between Barking and Docklands to grade-separated dual carriageway route. Despite Transport for London's anti-car policies, the scheme continues to go ahead because it is part of a private-finance DBFO contract.

Project Statistics

Cost
Unknown
Finance
DBFO
Estimated duration of works
2004

Progress

March 2003
Movers Lane underpass open.
November 2003
Beckton Flyover and Prince Regent Lane underpass open.
December 2003
East India Dock Link tunnel open in both directions.
October 2004
Canning Town Flyover alterations complete.
May 2006
Other than final clean-up operations, work is now complete.