A361 Barnstaple Western Bypass

You are here: Home - Futures - A361 Barnstaple Western Bypass

Scheme Outline

Construction of a new single two-lane route to the west of Barnstaple, connecting the A39 Atlantic Highway with the A361 North Devon road. The scheme includes a new 400m bridge over the River Taw, and will provide for the potential reopening of the railway line beyond Barnstaple.

Project Statistics

Cost
£40m
Finance
Devon CC
Estimated duration of works
2005-2007
Length of new road
Unknown

Progress

Feb 2005
Construction work begins.
July 2005
The southern terminal roundabout has been completed.
March 2006
New link roads and Sticklepath roundabout were opened on 18 March. The existing A3125 on Sticklepath Hill will now be closed and the old railway bridges demolished.
August 2006
The old railway bridges have now gone!
March 2007
The downstream bridge and station viaduct are now complete, earthworks are almost done and the Braunton Road junction is also nearing completion. The road is due to open in April.
May 2007
The new road opens to traffic.

More Information

Website
www.barnstaplebypass.com

With thanks to David Brown, Gerry McKenna and Jim Rayner for information on this page.