A64 Bilbrough Top Improvement
You are here: Home - Futures - A64 Bilbrough Top Improvement
Scheme Outline
Replacement of the existing crossroads on the A64 between Tadcaster and York with a grade-separated junction, including the installation of a new flyover. This section of road is running well under capacity, with substandard junctions and a poor alignment. It was built during the 1930's, but at each end is connected directly on to modern grade-separated dual carriageway. Bilbrough Top is one of the most dangerous junctions on the route.
Project Statistics
- Cost
- Unknown
- Finance
- Highways Agency
- Estimated completion of works
- 2005
Progress
- September 2004
- Construction of the new flyover is well under way.
- July 2005
- The new junction is opened to traffic.
With thanks to Simon Ward for information on this page.