M11 J8 Stansted

You are here: Home - Futures - M11 J8 Stansted

Scheme Outline

Provision of new free-flow links between the Stansted Airport approach road and the M11 to the south to ease chronic congestion at the junction. Alteration of junctions to allow the new A120 to flow directly onto the M11.

Timeline

1974
Stansted Airport opens, along with the corresponding section of M11.
1990
Complaints made concerning the congestion at junction 8: the existing roundabout interchange is no longer adequate.
2001
Work on new third-level flyovers between M11 to south and Stansted approach road begins.

Project Statistics

Cost
£36.5m
Finance
Central government/BAA
Estimated duration of works
1.5 years

Progress

2002
Carriageway diverions complete. Flyover structures in place.
2003
New junction opens to traffic.