M25 Holmesdale Tunnel
You are here: Home - Futures - M25 Holmesdale Tunnel
Scheme Outline
Properly called the M25 Holmesdale Tunnel Refurbishment and Junction 25 Improvements. The works will provide a third lane eastbound through junction 25 (previous works provided the third lane westbound), and widen the adjacent Holmesdale Tunnel to dual four lane. It will also provide essential refurbishment work on the electrical and mechanical equipment within the tunnel.
Project Statistics
- Cost
- £75m
- Finance
- Central Government
- Estimated duration of works
- 2005-2007
- Length of works
- 2 miles
More Information
- Website
- www.highways.gov.uk/...
Progress
- July 2007
- The eastbound lane was opened this month, ahead of schedule, and the speed limit through the roadworks was increased accordingly. The westbound exit and eastbound entry are both still closed.
- September 2007
- Works were finally completed in early September.
With thanks to Adrian Easton and Rob Fairhead for information on this page.