M4 J11 Reading
You are here: Home » Futures » M4 J11 Reading
CBRD Futures is no longer being updated as of July 2012 and information on this page may now be out of date.
- Type
- Junction improvement with some parts under motorway restrictions
- Status
- Completed
- Authority
- Reading Borough Council
- Cost
- £ 65m
- Finance
- Reading Borough Council/Central Government
- Timescale
- 2007-2010
Scheme Outline
Reconstruction of M4 junction 11, the connection point for the A33 and large parts of Reading. The junction improvements will add a new gyratory system around the outside of the existing roundabout, with the current bridges used for a bus priority route through the middle of the new junction. It will facilitate park and ride facilities that are proposed close to the site.
Progress
| 14 August 2006 | Government gives approval to the scheme, though the public inquiry is not yet fully complete. |
|---|---|
| 14 January 2008 | Preparatory works have already taken place with the erection of an acoustic noise barrier on Basingstoke Road near Kingsley Close. Funding approval from the Department for Transport is expected in February, after which work should begin in May. |
| 14 May 2008 | Tree clearance took place in February, and now the site compound is under construction. |
| 24 May 2010 | The new motorway bridges are mostly complete. The new roundabouts in South Reading are close to completion. Traffic from M4 J11 into Reading temporarily follows a different route while another roundabout is completed. |
More information
- Official website
- reading.gov.uk/junction11
- Official website
- wokingham.gov.uk/junction11
It's over!
This scheme has been completed, so it's no longer possible to edit any of the information on this page.
This scheme was last updated on 8 January 2011.