- Type
- Road with some parts under motorway restrictions
- Status
- Completed
- Authority
- Highways Agency
- Cost
- Unknown
- Finance
- Central Government
- Length
- Unknown
Scheme Outline
Works on the notorious Switch Island interchange to improve capacity and provide for a potential new connection. The Highways Agency is billing this scheme as a large-scale improvement but it is seen by many as small-scale fiddling.
Progress
| 14 October 2005 | Work has now started on the site. |
|---|---|
| 14 March 2006 | Work on the junction is now complete, with a new layout and an extra lane onto the junction from the M57. |
It's over!
This scheme has been completed, so it's no longer possible to edit any of the information on this page.