A10 Foxton Railway Crossing
You are here: Home » Futures » A10 Foxton Railway Crossing
- Type
- Bypass or realignment for use by all traffic
- Status
- In planning or on hold
- Authority
- Cambridgeshire County Council
- Cost
- £6.5m
- Finance
- Unknown
- Timescale
- 2009-2011
- Length
- 1.0 km (0.6 miles)
Scheme Outline
Replacement of the existing level crossing with a bridge over the railway (approximately 100m further west), with the existing level crossing being closed to traffic (except for pedestrian access).
This is a venerable project, appearing in the 1954 Cambridge County Development Plan, and probably even earlier.
More information
- Cambridgeshire Local Transport Plan 2004-2011 [PDF]
- www.cambridgeshire.gov.uk/.../LTP04C7.pdf
If you know more
If you have more details on this scheme - a correction to the information shown here or an update on the progress of works - please share your knowledge.
With thanks to Toby Speight for information on this page. This scheme was last updated on 13/11/2008.