A7 Auchenrivock Improvement Project

You are here: Home » Futures » A7 Auchenrivock Improvement Project

Type
Road for use by all traffic
Status
Completed
Authority
Transport Scotland
Cost
Unknown
Finance
Unknown
Timescale
2008-2009
Length
2.3 km (1.4 miles)

Scheme Outline

Bypassing a slow and winding section with a smooth offline upgrade, increasing safety and opportunities to overtake. The new road will still be single carriageway.

Progress

20 November 2008
Not a great deal can be seen from the present A7, but the foundations are in place.
28 May 2009
This scheme is almost complete now. The new road was being used on 26 May 2009 although there were still traffic control lights at each end where the old road joins the new.
21 June 2009
The new road is now open to traffic.

More information

Official website
www.transportscotland.gov.uk

This scheme has been completed, and is no longer open to updates.

With thanks to Hamish Scott, Tony Dickinson and Daniel Warrington for information on this page. This scheme was last updated on 21/06/2009.