A1(M) Bramham - Wetherby

You are here: Home » Futures » A1(M) Bramham - Wetherby

Type
Road under motorway restrictions
Status
Completed
Authority
Highways Agency
Cost
£68m
Finance
Central Government/DBFO
Timescale
2007-2009
Length
9.7 km (6.0 miles)

Scheme Outline

Upgrade of the existing dual three-lane all-purpose dual carriageway A1 to dual three-lane motorway standard, linking the motorway sections at Bramham and Wetherby. The works will involve closing the junctions at Bramham and south of Wetherby. Many local residents are unhappy with the plans as they will put all traffic between the A1 and A58 onto the narrow A659, which is widely thought to be unsuitable. The works will also provide a single-carriageway all-purpose road on the inside of the new Wetherby Bypass motorway to cater for local traffic.

Progress

Summer 2002
Department for Transport announces planned upgrade.
June 2007
Some tree clearance has taken place near the Wharfe bridge, and the road for non-motorway traffic has now been marked between Bramham and the A659. Ground works have been started in some places.
August 2007
Bramham lay-by and A58 Thorp Arch junction are both now closed permanently. Work is well advanced on the new link road alongside the A1, and preparatory work has begun for the new Wharfe Bridge.
June 2008
The local access road between Wetherby and the A64 is now open to traffic in both directions, with access closed off at the old Bramham junction. Work is still very much in progress on the Wetherby Bypass with seemingly a long way to go.
July 2008
The original overbridge at Wetherby Grange has now been demolished, meaning that much of the work south of Wetherby is now nearing completion.
26 May 2009
All looks ready to open, though it was still restricted to two lanes each way on 25th May.
9 June 2009
Junction numbering to be amended at Hook Moor to become consecutive.
10 August 2009
The Highways Agency website reports that "the road becomes fully operational as a three-lane motorway in both directions today (31 July 2009), in time for the summer holidays". Traffic management measures have been cleared away and the road is fully open to traffic.

More information

Website
www.highways.gov.uk/.../5541.aspx

This scheme has been completed, and is no longer open to updates.