Scheme Outline
Upgrade of the existing single two-lane route, which forms the main gateway into Nottingham from the South and the West Midlands. The route will be mostly dual two-lane with grade separated junctions, but reduces briefly to single four-lane approaching Clifton where land space is restricted. This last section will have at-grade roundabout junctions. Grade separated junctions will serve Ratcliffe Power Station, Barton-in-Fabis, and a potential Park and Ride site. The dualled section will terminate at Crusader Roundabout. Construction may now include construction or provision for a tram or rail line to East Midlands Airport.
Project Statistics
- Cost
- £90m
- Finance
- Highways Agency
- Estimated completion of works
- 2008-2011
- Length of works
- 8 miles
Progress
- January 2007
- Laing O'Rourke is appointed to develop the proposals.
- March 2006
- Local media reports that an announcement about the selected contractor is imminent, but a public inquiry will still be necessary.
More Information
If you know more
If you have more details on this scheme - a correction to the information shown here or an update on the progress of works - please click here and share your knowledge.
With thanks to Tim Mollart, Andy Kettles, John Morgan, Chris Williams and Gerry McKenna for information on this page.