Open Jct Section
1975 J23-24 South Mimms → Potters Bar
1976 J12-13 Thorpe → Egham
1976 J17-19 Maple Cross → Hunton Bridge
1976 J6-8 Godstone → Reigate
1977 J2-3 Dartford → Swanley
1979 J5-6 Sundridge Road → Godstone
1980 J11-12 Chertsey → Thorpe
1980 J5 Dunton Green → Sundridge Road
1981 J13 Egham → Yeoveney
1981 J24-25 Potters Bar → Waltham Cross
1982 J13-14 Yeoveney → Heathrow Spur (A3113)
1982 J29-31 North Ockenden → Mar Dyke
1983 J27-29 Theydon Garnon → North Ockenden
1984 J25-27 Waltham Cross → Theydon Garnon
1985 J14-15 Heathrow Spur (A3113) → M4
1985 J15-16 M4 → Iver Heath
1985 J16-17 Iver Heath → Maple Cross
1985 J8-10 Reigate → Wisley
1986 J19-23 Micklefield → South Mimms
1986 J1a-2 Dartford Tunnel Southern Approach
1986 J3-5 Swanley → Dunton Green