A13 Thames Gateway

Scheme outline

Upgrade of the A13 between Barking and Docklands to grade-separated dual carriageway route. Despite Transport for London's anti-car policies, the scheme continues to go ahead because it is part of a private-finance DBFO contract that was let when the A13 was in the hands of the Highways Agency.

This scheme was completed in and we're no longer accepting updates or changes to this page.

Timescale
2000-2004
Cost
Unknown
Status
Completed
Type
Other upgrade
for use by all traffic
Highway authority
Funding
DBFO

Progress

This scheme has been completed and CBRD is no longer accepting progress updates.
14 March 2003

Movers Lane underpass open.

14 November 2003

Beckton Flyover and Prince Regent Lane underpass open.

14 December 2003

East India Dock Link tunnel open in both directions.

14 October 2004

Canning Town Flyover alterations complete.

14 May 2006

Other than final clean-up operations, work is now complete.