A3 Hindhead Tunnel

Scheme outline

Realignment of the A3 into dual two lane bored tunnels, and grade-separation of the junctions at each end of the Hindhead section, removing the final section of single-carriageway between London and Portsmouth and the notorious Devil's Punchbowl hill. The scheme also removes traffic from an Area of Outstanding Natural Beauty.

The tunnel, when complete, will be the longest road tunnel in the UK.

There will be a Traffic Restriction Order in effect, prohibiting pedestrians, cycles, invalid carriages, animals and motorcycles under 50cc.

This scheme was completed in and we're no longer accepting updates or changes to this page.

Timescale
2008-2010
Cost
£
371m
Status
Completed
Type
Bypass or realignment
for use by all traffic
Highway authority
Funding
Central Government

Progress

This scheme has been completed and CBRD is no longer accepting progress updates.
14 October 2006

The government approves the scheme and work is due to start in early 2007.

14 January 2007

Work starts on the tunnels, with an exhibition held at Grayshott to mark the scheme's inauguration.

14 April 2007

The residents of Haslemere - now finally getting the bypass they need - are actively petitioning against the expected influx of foreign construction workers, who would be housed in a special work site nearby. They fear the impact this might have on the local 'economy', including house prices.

14 February 2008

Work has started on excavating the tunnels.

14 June 2008

Excavation work is now in full swing, with systems of conveyor belts constructed at the tunnel portals to remove the spoil.

20 January 2009

There are now 289 metres to go before tunnel breakthrough.

8 February 2009

Tunnelling from the north and the south ends is gathering speed. As of 1 February 2009 there were 59 metres to go to breakthrough on the northbound tunnel and 141m in the southbound tunnel.

26 February 2009

The northbound tunnel broke through at 2.34 this afternoon.

2 November 2010

The northbound end of the bypass is now surfaced and linked in with the A3 mainline. Traffic is using temporary slips to rejoin the old alignment through Hindhead Common. At the south end, the grade separated junction is complete and the road is currently being surfaced. Properties on the old (online) upgrade at Kempshott now have a local access road.

25 December 2010

New signage being installed north and south, roads now laid in both tunnels and installation of electrical and safety systems well under way in both tunnels. The scheme is now only 8 months from completion.

14 June 2011

An emergency training excerise was held in the tunnel today. The road is due to open in the next month.

7 July 2011

The Southbound Tunnel is to open first in the next week, followed by the northbound shortly after.

20 July 2011

Opening date for southbound tunnel now confirmed as the 27th July. Northbound to be a 'few days later'.

29 July 2011

The northbound tunnel opened to traffic today.

More information

Routes
Region

With thanks to Michael Pritchard, Adam Meara, John and Gummybear for information on this page.