A40 Wolvercote Roundabout Improvement

You are here: Home » Road Schemes » A40 Wolvercote Roundabout Improvement

Scheme Outline

Scheme details

Timescale
July 2015-September 2016
Status
Under construction
Type
Junction improvement for use by all traffic
Cost
£ 10m
Authority
Oxfordshire County Council
Region: South East
Finance
Oxfordshire County Council

Improvements to the A40/A44 roundabout junction at Wolvercote north-west of Oxford.

The scheme also includes Cutteslowe (or Summerstown) Roundabout and the section of single carriageway A40 linking the two. Improvements include signalising both roundabouts and adding safer pedestrian crossing facilities.

An additional lane will be provided on the A40 for eastbound traffic between the two roundabouts.

Is this information out of date? Update this page »

Progress

27 December 2016 Junction re-modelling complete. Cuttleslowe roundabout has been widened and traffic lights added to each entry point, some with dedicated bus lane signals. The A40 between Cuttleslowe and Wolvercote has been re-marked so there are now two lanes eastbound and one westbound. At Wolvercote entry to the junction from the A40 west is now traffic light controlled, with three approach lanes, which should help large or long vehicles get onto the roundabout more easily.

What's happening on this scheme? Add a progress report »

More information

Official website
Oxfordshire County Council: A40 Wolvercote and Cutteslowe roundabouts

Have you found more information? Add a new link »

Other schemes on the A40

CBRD also has details on the following road schemes happening on the A40.

With thanks to Martin Hazel for information on this page.

This scheme was last updated on 3 January 2017.