A43 Upgrade

You are here: Home » Road Schemes » A43 Upgrade

Scheme Outline

Scheme details

Timescale
2000-2002
Status
Completed
Type
Completedfor use by all traffic
Cost
£ 56.6m
Authority
Highways England
Region: East Midlands
Finance
Central Government
Length
16 km
10 miles

Upgrade of A43 between Towcester and the M40 to dual two lane standard, including some realignment. Also includes reconstruction of the junction with the M40.

Progress

14 November 2010 Construction work begins.
14 November 2010 Completion date of Summer 2002 is missed. Work is, however, almost complete by Autumn.

It's over!

This scheme has been completed, so it's no longer possible to edit any of the information on this page.

This scheme was last updated on 22 October 2008.