Scheme Outline

Scheme details

Timescale
Summer 2019 - 2022
Status
Preparation of legal orders and public inquiry
Type
Upgrade to existing road for use by all traffic
Cost
£ 400m
Authority
Welsh Assembly Government
Region: Wales
Finance
Welsh Government
Length
14 km
8 miles

Upgrade of the existing single three-lane A465 Heads of the Valleys Road between Dowlais Top and Hirwaun to provide a grade-separated dual two-lane expressway.

This scheme will be the final upgrade of the complete route from Abergavenny to Neath and will complete the continuous dual carriageway route between the A40 and M4 that has been progressively constructed since the mid-1970s.

The nine-mile section of single carriageway road to be upgraded is the final remaining section of route built in the early 1960s, and comprises the bypass around the north of Merthyr Tydful and an exposed section on high ground to the west of the town before the descent towards Hirwaun. It includes a significant number of major bridges and other structures, and passes through several built-up areas, so the widening works will be particularly complex.

Is this information out of date? Update this page »

What's happening on this scheme? Add a progress report »

More information

Official website
Welsh Government: Dowlais Top to Hirwaun (Section 5 and 6)

Have you found more information? Add a new link »

Other schemes on the A465

CBRD also has details on the following road schemes happening on the A465.

With thanks to Matt Tovey for information on this page.