Scheme outline

Construction of a new single two-lane road from Switch Island (the interchange of M57 and M58) to the A565 at Thornton, relieving the A5207 Northern Perimeter Road of through traffic.

The new road is roughly on the line of the planned northward continuation of the M57, a motorway scheme that was proposed in the 1970s but which was never built. The new road completes the onward link from the M57 towards Formby and Southport at considerably reduced cost.

This scheme was completed in and we're no longer accepting updates or changes to this page.

Timescale
2013-2015
Cost
£
20.4m
Status
Completed
Type
Bypass or realignment
for use by all traffic
Highway authority
Funding
DfT/Sefton Council

Progress

This scheme has been completed and CBRD is no longer accepting progress updates.