A63 Selby Bypass

You are here: Home » Road Schemes » A63 Selby Bypass

Type
Road for use by all traffic
Status
Completed
Authority
Highways Agency
Cost
Unknown
Finance
Central Government
Timescale
2001-2004
Length
11.2 km (7 miles)

Scheme Outline

Construction of a new bypass to Selby in North Yorkshire to two-lane single carriageway standard, including overbridges across minor roads and a new crossing at the Ouse. Roundabout junctions with the A19, A1041 and at each end.

Progress

14 December 2001 Preliminary works, land purchase.
14 April 2002 Land grading and early work on bridges.
14 December 2002 A1041 roundabout built and in operation; overpass across the Brayton to A1041 road is complete.
14 July 2004 Problems with the swing bridge are fixed and the bypass opens to traffic on June 15.

It's over!

This scheme has been completed, so it's no longer possible to edit any of the information on this page.

This scheme was last updated on 26 October 2008.