A66 Dualling Scotch Corner - Stephen Bank

You are here: Home » Road Schemes » A66 Dualling Scotch Corner - Stephen Bank

Scheme Outline

Scheme details

Timescale
2006-2007
Status
Completed
Type
Completedfor use by all traffic
Cost
Unknown
Authority
Highways England
Region: Yorkshire and the Humber
Finance
Central Government
Length
15.28 km
9.5 miles

Upgrade of the existing substandard A66 route from Scotch Corner on the A1 to the County Durham border. The scheme is broken into two sections, Scotch Corner to Carkin Moor and Greta Bridge to Stephen Bank. It is likely that the road will be upgraded to dual two-lane all-purpose, but will not be grade-separated.

Progress

14 June 2006 Work is scheduled to begin shortly on the section between Scotch Corner and the County Durham border.
14 July 2006 Work has started on dualling the section between Scotch Corner and Greta Bridge.
14 September 2007 Work is complete and the new roads are open.

It's over!

This scheme has been completed, so it's no longer possible to edit any of the information on this page.

This scheme was last updated on 26 October 2008.