Scheme outline

Completion of the link between M74 at Polmadie and M8/M80 at Provan. Two earlier phases have already been completed: Phase 1 is New Rutherglen Road, Oatlands, completed in 2007; Phase 1A runs from Polmadie to Shawfield, completed in 2010; and Phase 2 runs from the River Clyde to Parkhead, opened in 2012.

This final section comprises 1.4 km of 4-lane carriageway, with 2 terminal and 2 intermediate junctions. An eight-span viaduct will carry the road over the Glasgow-Airdrie railway line.

Timescale
2016-2018
Cost
£
60m
Status
In preparation
Type
New road
for use by all traffic
Highway authority
Funding
Local Government

Progress

What's happening on this scheme? You can add a progress update if you know more. Add a progress update
13 November 2016

Work has started on removing the old railway bridge walls and the embankment at the bottom of Todd Street at its junction with Carntyne Road.