A78 Saltcoats Bypass

Scheme outline

Construction of a new partially dual-two lane and partially single carriageway road to bypass the towns of Stevenston, Saltcoats and Ardrossan in North Ayrshire.

This scheme was completed in and we're no longer accepting updates or changes to this page.

Timescale
2003-2005
Cost
£
30m
Status
Completed
Type
Bypass or realignment
for use by all traffic
Highway authority
Funding
Scottish Executive

Progress

This scheme has been completed and CBRD is no longer accepting progress updates.
14 October 2004

The southern terminal roundabout is now in place but not fully open. The Sharphill Road interchange has recently been started, and signs are now claiming a May 2005 completion.

14 January 2005

Road is completed and opens to traffic.