M4 J16 Improvement

Scheme outline

Work to improve the capacity of the roundabout at M4 junction 16 west of Swindon. The roundabout is already fully signalised and in order to provide space for more traffic and support nearby planned developments reconstruction work is now being carried out.

The changes will see a right-turn introduced from the A3102 Swindon Road and the B4005 Hay Lane on the south side of the roundabout which will bypass the junction completely, and changes to the A3102 Great Western Way to the north including remodelling of the next set of traffic signals towards Swindon.

Timescale
2017-2018
Cost
£
11.5m
Status
Under construction
Type
Junction improvement
for use by all traffic
Highway authority
Funding
Swindon and Wiltshire Local Enterprise Partnership

Progress

What's happening on this scheme? You can add a progress update if you know more. Add a progress update