M5 J12 Improvements

Scheme outline

The aim of this scheme is to improve traffic flow by increasing the capacity of the junction. This will be achieved by adding lanes to the sliproads, roundabouts, and overbridge, and by building new, dedicated filter lanes north- and southbound between the M5 and the B4008 (A38) to Gloucester. The junction will also be signalised.

This scheme was completed in and we're no longer accepting updates or changes to this page.

Timescale
2011
Cost
£
4.2m
Status
Completed
Type
Junction improvement
with parts under motorway restrictions
Highway authority
Funding
Central Government/Local Developer

Progress

This scheme has been completed and CBRD is no longer accepting progress updates.
10 September 2010

Work began on 6 September 2010, and is scheduled to continue for 14 weeks. All work will be carried out between the hours of 8pm and 6am, during which time the junction will be closed to all traffic.

4 February 2011

This scheme was completed at the end of January 2011.