M6 Birmingham Box ATM Phase 3

Scheme outline

Introduction of Active Traffic Management technology between junctions 5 and 8 of the M6 (including the M5 link roads), in order to relieve congestion.

This scheme was completed in and we're no longer accepting updates or changes to this page.

Timescale
2012-2014
Cost
£
126m
Status
Completed
Type
Other upgrade
under motorway restrictions
Highway authority
Funding
Central Government

Progress

This scheme has been completed and CBRD is no longer accepting progress updates.
9 November 2010

Funding for this scheme was confirmed by the Transport Secretary following the recent autumn spending review.

25 April 2011

Construction is scheduled to start in 2012/2013, according to the Highways Agency.

3 January 2012

The contractor for this scheme (Carillion) was appointed today. The main phase of construction is now expected to start between April and June 2012.

18 April 2012

Average speed cameras have now been installed between junctions 5 and 8.

10 May 2012

Work on this scheme is now well underway. A controversial lane drop northbound at J6 is causing major traffic issues in rush hours.

7 October 2014

The Highways Agency are listing a completion date of August 2014, but the scheme is still classed as 'current'.

13 October 2014

The scheme has been completed, with small scale ancillary and environmental works continuing for a few weeks.

More information

Routes
Region

With thanks to Scott Spencer, Matt Pryce and Michael Pritchard for information on this page.