M6 Junction 32 Improvement

You are here: Home » Road Schemes » M6 Junction 32 Improvement

Type
Road under motorway restrictions
Status
Completed
Authority
Highways Agency
Cost
£ 4.78m
Finance
Central Government
Timescale
2009
Length
Unknown

Scheme Outline

Widening of the southbound carriageway of the M6 to provide three full lanes through Junction 32, which has been a severe bottleneck for many years. The widening will not replace the existing structures, leaving an intermittent hard shoulder through the junction.

Progress

23 November 2008 Advance works appear to have begun before the official start of work. Gantries approaching the junction have had modifications, with one being removed. New barriers have been installed for a new gantry installation.
20 January 2009 Preliminary barrier works are all complete, and information boards marking the official start of work as January 26th are in place. Overnight closures are scheduled for numerous weekends throughout February.
27 January 2009 Closure and Diversion dates are now on the Highways Agency website.
12 April 2009 Southbound tarmac paving works almost complete, with level connections to existing carriageways still to made.
1 June 2009 Three southbound lanes are now open, with hard shoulder works still taking place. There is now a 'tiger-tail' merge for traffic using the M55 entry sliproad.
10 June 2010 Scheme has been fully completed for some time and has removed the major bottleneck once caused here.

More information

Official website
highways.gov.uk/roads/projects/19189.aspx

It's over!

This scheme has been completed, so it's no longer possible to edit any of the information on this page.

This scheme was last updated on 12 June 2010.