M6 Junction 32 Improvement

Scheme outline

Widening of the southbound carriageway of the M6 to provide three full lanes through Junction 32, which has been a severe bottleneck for many years. The widening will not replace the existing structures, leaving an intermittent hard shoulder through the junction.

This scheme was completed in and we're no longer accepting updates or changes to this page.

Timescale
2009
Cost
£
4.78m
Status
Completed
Type
Junction improvement
under motorway restrictions
Highway authority
Funding
Central Government

Progress

This scheme has been completed and CBRD is no longer accepting progress updates.
23 November 2008

Advance works appear to have begun before the official start of work. Gantries approaching the junction have had modifications, with one being removed. New barriers have been installed for a new gantry installation.

20 January 2009

Preliminary barrier works are all complete, and information boards marking the official start of work as January 26th are in place. Overnight closures are scheduled for numerous weekends throughout February.

27 January 2009

Closure and Diversion dates are now on the Highways Agency website.

12 April 2009

Southbound tarmac paving works almost complete, with level connections to existing carriageways still to made.

1 June 2009

Three southbound lanes are now open, with hard shoulder works still taking place. There is now a 'tiger-tail' merge for traffic using the M55 entry sliproad.

10 June 2010

Scheme has been fully completed for some time and has removed the major bottleneck once caused here.

More information

Routes
Region