M60 J8-18 and M62 J18-20 Smart Motorway

Scheme outline

Installation of Smart Motorway technology to a substantial length of M60 and M62, stretching from M60 J8 (the Carrington Spur near Trafford) to M62 J20 (the A627(M) between Oldham and Rochdale).

The scheme will introduce variable speed limits, hard shoulder running and new emergency refuge areas in an attempt to increase capacity and improve traffic flows on this congested length of motorway.

This scheme is part of the Smart Motorways programme of works.

Timescale
2014-2017
Cost
£
201.6m
Status
Under construction
Type
Other upgrade
under motorway restrictions
Highway authority
Funding
Central Government

Progress

What's happening on this scheme? You can add a progress update if you know more. Add a progress update
15 June 2016

The latest phase of a major project to tackle congestion and improve journey times on the M60 and M62 is due to start on Tuesday 14 June. Contractors for Highways England will begin work to upgrade 56 overhead gantries on the 17-mile smart motorway route between junction 8 of the M60 near Sale and junction 20 of the M62 near Rochdale, so that they can be fitted with new electronic signs.

21 December 2017

The electronic signs on the section between M60 J8-10 are now in use.

10 January 2018

The electronic signs are now in use on the M62 section, between J18 and J20. The hard shoulder on this stretch also opened to traffic just before Christmas - but the whole scheme is still restricted to 50mph at all times while finishing works and testing takes place.

14 January 2018

On the M60 between J10 and J14, the narrow lanes have been reconfigured, and barrier work appears to be taking place.