M62 J6 Improvement

Scheme outline

Construction of new free-flow sliproads at the interchange of the M62 and M57 to alleviate congestion on the major turning movements, currently catered for by a roundabout. The new links will include a south-to-east link, requiring the realignment of a local road that currently uses the junction, and a 270-degree loop west-to-north, passing over and under existing sliproads.

This scheme was completed in and we're no longer accepting updates or changes to this page.

Timescale
2007-2009
Cost
£
38m
Status
Completed
Type
Junction improvement
with parts under motorway restrictions
Highway authority
Funding
Highways Agency

Progress

This scheme has been completed and CBRD is no longer accepting progress updates.
14 March 2006

Plans have been published, the cost announced, and the scheme has gone to public consultation.

14 May 2006

Construction work began last month on land adjacent to the junction.

14 December 2008

The Highways Agency advise that work on this junction is fully completed.