This scheme aims to improve safety and reduce congestion on the motorway network surrounding the Baillieston (M8/M73) and Maryville (M73/M74) Interchanges. It also forms the link between a number of improvements to the motorway network in this area (M80 Stepps to Haggs, M74 Completion, M8 Baillieston to Newhouse), and is therefore expected to improve traffic flow between these projects.

The package of junction and road improvements includes the following:

1. Widening the M8 eastbound to four lanes from J10 (Easterhouse) to J8 (Baillieston).

2. Widening the M73 to four lanes each way between the Ballieston and Maryville Interchanges.

3. Widening the M74 to four lanes each way between junctions 3 (Daldowie) and 5 (Raith). The southbound M74 will be widened to four lanes as far as junction 6 (Hamilton).

This scheme will be combined with the M8 Baillieston to Newhouse and M74 J5 (Raith) Improvement and delivered as a single contract.

This scheme was completed in and we're no longer accepting updates or changes to this page.

Timescale
2014 - 2017
Cost
£
53m
Status
Completed
Type
Other upgrade
under motorway restrictions
Highway authority
Funding
Scottish Government

Progress

This scheme has been completed and CBRD is no longer accepting progress updates.
30 March 2012

The procurement process starts today.

2 July 2015

This scheme is now under construction.

17 December 2015

The new section of A725 near Shawhead is now surfaced all the way to the new bridge.

15 August 2017

The scheme was officially opened by First Minister Nicola Sturgeon on the 14th August.