M90 Forth Road Bridge Replacement

Scheme outline

Construction of a new cable-stayed bridge across the Forth Estuary to carry a dual two-lane road with hard shoulders. The bridge will be sited to the west of the existing Forth Road Bridge, which is suffering serious structural faults. The new bridge was rushed through the planning process and fast-tracked to construction, because when the scheme was first proposed it was feared that the existing Forth Road Bridge may have been too weak to carry heavy goods vehicles even before the new bridge could be brought into service.

The proposed new cable-stayed bridge will have three slender single column towers and will be 2.7km long, including approach viaducts. The road carried by the bridge will be designated as a southward extension of the M90.

To the south of the bridge, a new motorway standard road will link the crossing to the A90 and M9, making use of the M9 Spur. The spur has been reclassified M90, but will be separated from the new bridge by a short section of all-purpose road, so the M90 will be in two parts. To the north, the bridge will flow directly into the M90, incorporating junction enhancements at Admiralty and Ferrytoll, and road widening between those junctions.

This scheme was completed in and we're no longer accepting updates or changes to this page.

Timescale
2011-2017
Cost
£
2bn
Status
Completed
Type
New road
with parts under motorway restrictions
Highway authority
Funding
Scottish Executive

Progress

This scheme has been completed and CBRD is no longer accepting progress updates.
14 May 2008

Three preliminary contracts have been awarded, totalling £1.7 million, for topographical aerial surveys and ground investigation works.

23 January 2009

Public exhibitions are being held at the moment. The new road will not now terminate on the M9 but will tie in with the existing A90 on the south shore at the newly created Scotstoun Interchange which was created when the M9 spur was extended.

16 July 2009

Transport Scotland have announced that the Forth Replacement Crossing tender process has commenced.

17 November 2009

Legislation is now being presented to the Scottish Parliament. There is a big question mark over funding that is still outstanding.

26 May 2010

MSPs voted in favour of the new Forth crossing, allowing the project to proceed to the next parliamentary stage. Provided there are no major problems, work is expected to begin in 2011 and be completed by 2016.

25 December 2010

Final approval for the replacement bridge was given by the Scottish Parliament on 15 December 2010.

25 January 2011

The bridge has now received royal assent in Parliament and construction will begin later this year.

22 March 2011

The Scottish government has announced the preferred bidder for the Forth Replacement Crossing.

17 July 2011

The Principal Contract for the design, construction and completion of the Forth Replacement Crossing (FRC) has now been formally awarded to Forth Crossing Bridge Constructors (FCBC) consortium. Construction on the FRC is expected to begin during the summer of 2011. Contracts for the Intelligent Transport System (ITS) and the upgrade of the M9 at Junction 1a near Kirkliston have also been awarded.

23 September 2011

A mandatory 40mph speed limit came into force today in order to allow traffic management systems to be put in place on the M90 and A823(M), as part of the wider Forth Replacement Crossing scheme.

16 February 2012

Work has started at the M9 spur and there are now average speed camaras there.

11 October 2014

The cost of the Queensferry Crossing will be £50m lower than previously estimated. The revised budget is down to an upper limit of £1.4bn from £1.45bn.

16 December 2014

All three towers are well above deck level with the first deck sections under construction on temporary formwork. North and south approach viaducts are progressing.

17 March 2015

Speed restrictions are about to begin on the Forth Road Bridge - as the increasingly high towers of the new bridge are a distraction!

3 August 2015

The first cables have appeared, on the north side of the north tower.

21 October 2015

The old B800 overbridge at Scotstoun is to be demolished over the weekends of 24/25 October and 31 October/1 November. On the Fife side, the new northbound carriageway over Ferrytoll Junction is surfaced and painted ready for the next phase of traffic management (from Friday 23 October).

18 February 2016

The launching out of the north approach viaduct has begun, from the onshore construction site onto its two piers.

9 March 2016

North Approach Viaduct is now on top of both the N1 and N2 piers.

25 April 2016

Raising of the deck sections has now passed the halfway point - the 55th out of 110 sections was installed in March.

9 June 2016

Poor weather in April and May have pushed the completion date to March 2017.

12 August 2016

The northern deck section is now fully connected to its approach viaduct. This is the first of the four connections to be completed.

3 November 2016

The central tower's deck section has met that of the south tower, and they are being connected. The gap to the north tower deck is awaiting its final (shorter) section, and will be connected soon. Further north, the Ferrytoll roundabout is now circulating on the final alignment, albeit coned down to one lane only.

18 February 2017

On 3rd February, the last section of crossing was lifted into place, meaning the 1.7 mile bridge is now complete end-to-end.

17 March 2017

The new northbound on-slip at Ferrytoll is now fully open (direct from the roundabout). Work has begun at the northern end of the bridge to install the wind deflection fence onto the deck.

29 March 2017

Completion date has been pushed back again due to weather conditions. The crossing is now expected to open in late-July or August.

16 May 2017

The three tower cranes that have stood over the project for the last five years have now been dismantled.

4 July 2017

The bridge is to open at the end of August.

13 July 2017

Overhead matrix signs have been installed, cantilevered from the towers above the road deck. The bridge is scheduled to open to traffic on Wednesday 30th August, with a closure the subsequent weekend for 50,000 lucky people to walk across the bridge.

24 August 2017

The Queen, Prince Phillip and First Minister Nicola Sturgeon will attend official opening on 4th September.

30 August 2017

The Queensferry Crossing is now in use by A90/M90 traffic (not yet under motorway regulations). Work will now commence on the changes to the Forth Road Bridge.

4 September 2017

The new Queensferry Crossing was officially opened by the Queen.

7 September 2017

The Queensferry Crossing is now permanently open to traffic.

More information

Routes
Region

With thanks to Allan McPhail, Duncan Macknight, Ian Phillips, Peter, Toby Speight, Neil Kinmont, Michael Pritchard and Gerry McKenna for information on this page.